Gestern wurde mit dem Aufbau unseres Hauses begonnen. Als wir gegen 7.00 Uhr an der Baustelle ankamen, war der Bautrupp schon fleißig an der Arbeit. Die Vorbereitungszeit dauerte bis about 8.00 clock, then the first wall was lifted by crane from the truck. Already about 1 ½ hours later, all the walls on the ground floor in place. At noon, was already installed the ceiling elements. Then we went a bit slower because the arrival of a truck with the other House members had been somewhat delayed. However, it was the very hard-working construction crew Schwörer the roof in the shell until sunset to finish - a great achievement.